The concretors delivered the goods on Thursday and finished the slab, just in time for Easter. Now we really get a true picture of how much yard space is left and it looks pretty good for a nice flat space at the back and quite a large side yard because of our 20+ m frontage. Now we are up for our first big progress payment :(.
Fowler Homes got in touch with us this week about removing the excess dirt. They offered to do it at $550/12 tonne load. I found another contractor to do it for $300/load, starting first thing Tuesday morning. They will also move some up the back to use later in levelling the yard.
Fowler Homes Site Supervisor told me that the external plumbing should be completed next Thursday (1 week for slab curing) and then the frame should be delivered within the week following that. We also confirmed the mortar and joint type for our internal recycled press brick wall in the Meals Room - off white with a raked joint. Nice, nice, nice...
Although I'd love it to be quicker, progress has been reasonable so far. Fingers crossed it stays that way.
Showing posts with label variations. Show all posts
Showing posts with label variations. Show all posts
Sunday, 8 April 2012
Monday, 26 March 2012
Piers Me Off! (with pic)
Piering occurred today. Nice to see the progress but was given almost no notice to go and verify the depths. Watched for a while when a 3 m pier was dropped and started to think the worst regarding a variation - there was only an allowance for 50 lineal metres in the contract and I find out today there are 55 piers. Once we assessed all of the depths it came out as 89 m, 39 m over the allowance x $80/m = $3,120 unbudgeted. I am a bit 'piers'ed off! I reckon Fowler Homes could have predicted this. I had a look at my Wisdom Tender and they had given a fixed price! A definite trap for first time Builders. If you have a site affected by fill, consider the potential for piering variations.
The concrete pump arrived before I left so the piers should be filled today. Formwork, plumbing, reo and then lay slab - could all happen this week weather permitting and Fowler being on their game. Here's hoping.
The concrete pump arrived before I left so the piers should be filled today. Formwork, plumbing, reo and then lay slab - could all happen this week weather permitting and Fowler being on their game. Here's hoping.
![]() |
Piers drilled, setting up for filling |
Monday, 5 September 2011
From Sign On to Drawings - Delays, Delays, Delays...
To finalise the Fowler Homes tender in order to make it accurate for the drawings took a couple of iterations despite me giving clear instructions each time. After this we paid the first deposit of $5,000, negotiated down from $10,000 - Wisdom Homes only wanted $2,300 at this stage.
I had to ask what the next steps were as no information was offered. I was told that the drawings would take about 4 weeks. I follow up at 3.5 weeks and then again at 4.5 weeks and finally get them that night.
There are some minor errors and a few things I would like changed. It takes 4 days to get a variation detailing the amendments and changes. I sign and return within 30 minutes. I follow up 5 days later to find that the Rep did not realise I had returned it and she orders the drawings then. A week and a half later I finally complain about all of the delays and I get revisions that night with a promise for the Contract within 3 days.
I again follow up 4 days later to be told the boss is ill and it will come tomorrow.
As I had anticipated during the negotiations phase I have to chase every time in order to make progress. I am hoping to be in by Easter 2012. I think it is realistic but I also won't be surprised to be disappointed...
Have been pricing Solicitors to review the Contract. Ranges from $500 to $2,500 so worth shopping around. I will read it first to decide whether I think it is necessary or not.
In the meantime we have investigated a few variations:
I will keep you posted.
I had to ask what the next steps were as no information was offered. I was told that the drawings would take about 4 weeks. I follow up at 3.5 weeks and then again at 4.5 weeks and finally get them that night.
There are some minor errors and a few things I would like changed. It takes 4 days to get a variation detailing the amendments and changes. I sign and return within 30 minutes. I follow up 5 days later to find that the Rep did not realise I had returned it and she orders the drawings then. A week and a half later I finally complain about all of the delays and I get revisions that night with a promise for the Contract within 3 days.
I again follow up 4 days later to be told the boss is ill and it will come tomorrow.
As I had anticipated during the negotiations phase I have to chase every time in order to make progress. I am hoping to be in by Easter 2012. I think it is realistic but I also won't be surprised to be disappointed...
Have been pricing Solicitors to review the Contract. Ranges from $500 to $2,500 so worth shopping around. I will read it first to decide whether I think it is necessary or not.
In the meantime we have investigated a few variations:
- Bowral Dry Pressed Gertrudis Brown and plain Bowral Brown Dry Pressed brick upgrades were super expensive and we will not be going there.
- Austral Brick are having trouble supplying the Whitsunday range and are offering Metropolis in lieu. Austral emailed me a spreadsheet of jobs completed in the Metropolis range and I have done some drive-bys. It looks like we might go with Topaz.
- We had Bristile Classic concrete tiles thrown in free. Thought about Birch and Beach but all of the light coloured roofs I see around the place are covered in dirt. We are thinking Gunmetal now.
- We are going ahead with an internal brick wall in the Meals area done in recycled brick from the Recycled Brick Yard at Canterbury. Check out Google streetview of 46 Evans St Rozelle to see the effect. Should look hot.
I will keep you posted.
Subscribe to:
Posts (Atom)